Aaj kal solar rooftop lagwana bahut aasaan ho gaya hai, especially Government subsidy ke saath. Lekin approval process kaise hota hai? Kaunse documents chahiye? Kitne din lagte hain?
Is blog me hum solar rooftop approval process step-by-step detail me samjhenge.
1. Solar Rooftop Approval Process Kya Hota Hai?
Solar rooftop approval process ka matlab hai — government, DISCOM aur installer se permission lekar solar system ko legally install & connect karna.
Ye approval mainly 3 cheezon ke liye hota hai:
- Subsidy claim
- Net metering installation
- Safety compliance
2. Solar Rooftop Approval Process Step-by-Step
Step 1: PM Surya Ghar Portal Par Registration
Sabse pehle aapko official portal par apply karna hota hai:
👉 pmsuryaghar.gov.in
Yahan par aapko:
- State select
- DISCOM select
- Account number dalna hota hai
Isse verify hone ke baad aapka account create ho jata hai.
Step 2: Installer Select Karein
Portal par government-approved vendors ki list hoti hai.
Aapko unme se ek installer choose karna hota hai.
Installer:
- Site survey karta hai
- Load assess karta hai
- Proper system recommend karta hai
Step 3: Application Submit (With Required Documents)
Documents required:
- Aadhaar
- Electricity bill
- Photo of rooftop
- Bank passbook
- Signature
Installer aapki application portal par upload karta hai.
Step 4: DISCOM Verification
DISCOM (bijli board) aapka application verify karta hai.
Ye check karta hai:
✔ Load feasibility
✔ Consumer details
✔ System capacity
Approval milne me 7–15 days lagte hain.
Step 5: Solar Rooftop Installation
Approval ke baad installer system install karta hai:
- Structure fitting
- Panel mounting
- Inverter & wiring
- AC/DC distribution box
Is process me 1–3 days lagte hain.
Step 6: DISCOM Inspection
Installation ke baad DISCOM team aati hai aur:
✔ Safety check karti hai
✔ Earthing verify karti hai
✔ System commissioning approve karti hai
Inspection complete hone ke baad net meter installation approve hota hai.
Step 7: Net Meter Installation
DISCOM net meter install karta hai jo:
- Aapke grid export units ko measure karta hai
- Bill me adjust karta hai
Net meter lagne ke baad aapka solar officially active ho jata hai.
Step 8: Subsidy Claim & Release
After net meter installation:
✔ Installer portal par commissioning report upload karta hai
✔ DISCOM verification karta hai
✔ Subsidy release hoti hai (directly bank account me)
Subsidy release time: 30–90 days.
3. Solar Rooftop Approval Process Kitna Time Leta Hai?
| Step | Time |
|---|---|
| Application | 1 Day |
| DISCOM Approval | 7–15 Days |
| Installation | 1–3 Days |
| Inspection | 3–7 Days |
| Net Meter | 7–20 Days |
| Subsidy Release | 1–3 Months |
Total Time: 30–60 days average
4. Cost of Approval & Net Metering
Generally DISCOM net meter cost charge karta hai:
₹1,500 – ₹3,500 (state par depend karta hai)
Approval process ka koi extra charge nahi hota.
5. Solar Rooftop Approval Me Common Problems
❌ Application rejected
Reason: Documents mismatch
Solution: Installer se revise karwao
❌ Net meter delay
Reason: Stock shortage
Solution: DISCOM ko follow-up
❌ Rooftop space insufficient
Reason: Shadow / small area
Solution: High-efficiency panels lagao
6. Solar Rooftop Approval Tips
✔ Correct documents upload karein
✔ Verified installer choose karein
✔ Earthing proper maintain karein
✔ DISCOM inspection ke time present rahein
✔ Subsidy application track karte rahein
FAQs: Solar Rooftop Approval Process
Q1: Solar rooftop approval free hota hai?
Yes, approval free hota hai. Sirf net meter ka charge lagta hai.
Q2: Approval lene me kitna time lagta hai?
Usually 30–60 days.
Q3: Kya bina approval ke solar install kar sakte hain?
On-grid ke liye No, off-grid bina approval ke ho sakta hai.
Q4: Kya subsidy bina approval ke mil sakti hai?
Nahi, portal par apply karna mandatory hai.
Q5: Kaunse documents chahiye?
Aadhaar, bill, bank passbook, rooftop photos.
Conclusion
Solar rooftop approval process simple hai agar aap right installer aur correct documents provide karein.
Is process me registration → approval → installation → inspection → net meter → subsidy in steps ka follow karna hota hai.
Agar aap sahi procedure follow karte ho, aapka solar rooftop easily approve ho jayega aur subsidy bhi time pe mil jayegi.